Cost and Time Efficiency of Reinforced-Concrete Column Construction Using Conventional and Ready-Mix Methods: A Case Study of the Nurul Yaqin Mosque Project in Bumi Pajo Village

https://doi.org/10.59810/lejlace.v4i2.262

Authors

Keywords:

Construction schedule, Conventional concrete, Cost efficiency, Cost estimate, Ready-mixed concrete, Time efficiency

Abstract

This study compares the cost and time efficiency of conventional and ready-mix methods for reinforced-concrete column work in the Nurul Yaqin Mosque project, Bumi Pajo Village. Work volumes, unit prices, project cost estimates, and construction schedules were analyzed using field observations, literature, and project documentation. Conventional concrete had a unit price of IDR 1,238,000/m³, compared with IDR 1,514,506/m³ for ready-mixed concrete. Total costs were IDR 136,562,428 and IDR 141,276,996, respectively. The conventional method required 9 days, whereas ready-mix construction required 7 days. Ready-mix costs were increased by mixer-truck transportation, equipment operation, and restricted uphill access approximately 7 km from the national highway. Batching-plant production, however, shortened the placement duration. The conventional method was therefore more cost-efficient, while ready-mixed concrete was more time-efficient. Method selection should account for project accessibility, schedule requirements, quality control, and budget constraints.

References

Andriawan, Aan, and Winna Tan. 2021. “ANALISIS PERBANDINGAN BETON PRACETAK PRATEGANG DENGAN BETON KONVENSIONAL DITINJAU DARI ASPEK BIAYA DAN WAKTU (STUDI KASUS: RUMAH TINGGAL 2 LANTAI PERUMAHAN PERMATA RIVER VIEW).” Jurnal Kacapuri : Jurnal Keilmuan Teknik Sipil 4 (1): 190–200. https://doi.org/10.31602/jk.v4i1.5156.

Atika, E. Konstruksi, K. M. Studi, P., Sipil, T., Magister, P. Teknik, F., Dan, S., & Indonesia, U. I. 2021. No Title.

Fatoni, Ahmad, Miftahul Huda, and Priyoto Priyoto. 2024. “Analisis Perbandingan Biaya Dan Waktu Pelaksanaan Pelat Lantai Beton Panel Dan Beton Konvensional (Studi Kasus Proyek Pembangunan SMP Islam Terpadu AL-Irsyad Al-Islamiyah Kabupaten Pamekasan).” Jurnal Spesialis Teknik Sipil (JSpTS) 5 (1): 1–14. https://doi.org/10.30996/jspts.v5i1.10730.

Mulyono, T. 2004. Teknologi Beton. Yogyakarta: Andi.

Ngurah, I. G., & Angga, D. 2022. Oleh : i gusti ngurah deva angga pradnyanta 1915113018.

Nasir, Gustina M, M Yusuf Tuloli, and Aryati Alitu. 2022. “Optimasi Pelaksanaan Pengecoran Antara Beton Site Mix Dan Ready Mix Dari Batching Plant Pada Pekerjaan Pengendalian Banjir Sungai Bolango Kota Gorontalo.” Composite Journal 2 (2): 40–44.

Sastra Wibawa, I Made, I Gede Angga Diputera, and Ayulili Sagita Candra Devi. 2026. “ANALISIS PERBANDINGAN BIAYA DAN WAKTU PELAKSANAAN PENGECORAN BETON READY MIX DENGAN KONVENSIONAL PADA PEMBANGUNAN VILLA GUILHERME BERAWA, CANGGU, BALI.” Jurnal Ilmiah Teknik Universitas Mahasaraswati Denpasar (JITUMAS) 6 (1): 24–29. https://doi.org/10.36733/jitumas.v6i1.13957.

Soeharto, Iman. 1999. Manajemen Proyek (Dari Konseptual Sampai Operasional). Jakarta: Erlangga.

Sugiyono. 2019. Metode Penelitian Kuantitatif, Kualitatif, Dan R&D. Bandung: Alfabeta.

Tuloli, M. Y., Teknik, F., Gorontalo, U. N., Mix, R., & Plant, B. 2022. C o m p o s i t e j o u r n a l. 2(2): 40–44. https://doi.org/10.37905/cj.v2i2.53

Published

2026-09-19

How to Cite

Nurlaila, Asfarina, S., & Setiawan, W. (2026). Cost and Time Efficiency of Reinforced-Concrete Column Construction Using Conventional and Ready-Mix Methods: A Case Study of the Nurul Yaqin Mosque Project in Bumi Pajo Village. Local Engineering, 4(2), 83–88. https://doi.org/10.59810/lejlace.v4i2.262